Pharmacy Aseptic Suite Transformation

Sector

Healthcare

Location

North West

Service

Refurbishment

The programme included first and second fix mechanical and electrical installations, construction of airlock and gowning rooms, and installation of floor-to-ceiling welded hygienic wall systems (Gemclad) to create fully sealed environments. Advanced HVAC systems were integrated to deliver controlled air quality, filtration and pressurisation across interlocked spaces ranging from unclassified corridors to Grade D and Grade C cleanrooms, with Grade C providing the highest sterility. The project also included specialist flooring, sterile finishes, and full cleanroom validation and commissioning for oncology drug preparation, all delivered within a 16-week programme.

What we did

Our Pharmacy Aseptic Suite Transformation at Halton General Hospital involved the full strip-out and conversion of a former pharmacy intake and storage area into a highly specialised aseptic cleanroom facility within a live hospital environment.

Specifications

  • Full strip-out of former pharmacy intake and storage area
  • Design and construction of aseptic cleanroom facility
  • Installation of floor-to-ceiling welded hygienic wall systems (Gemclad)
  • Specialist mechanical and electrical (M&E) installations
  • Air handling systems with controlled pressure regimes
  • Cleanroom validation (Grade C and Grade D environments)
  • Airlock and gowning room construction
  • First and second fix M&E works
  • Specialist flooring and sterile finishes
  • Commissioning of aseptic suite for oncology drug preparation

Project Overview

Number of Weeks

16

Project Value

£650K

+

Key challenges included integrating complex HVAC systems to maintain strict pressure regimes, constructing ultra-clean sealed environments, and delivering specialist M&E works within an existing footprint. These were overcome through a carefully sequenced programme, from strip-out to commissioning, and close collaboration with Estates and Pharmacy teams.

Working in a live environment required detailed planning, controlled access, and adherence to infection prevention protocols. The result is a high-performance cleanroom facility that ensures contamination control, improves operational efficiency, reduces reliance on external supply chains, and supports faster, patient-specific treatment delivery.

Innovations, challenges, solutions

Through our specialist healthcare expertise, we delivered a GMP-compliant aseptic facility within an operational hospital, enabling on-site preparation of injectable medicines including chemotherapy and intravenous nutrition.

“CLC has worked closely with the Trust Estates and Pharmacy teams on delivering this project as part of the Trust’s capital programme. This facility will be vital in allowing us to manufacture aseptic drugs on site, improving efficiency, reducing costs, and enhancing patient care through faster, tailored treatments.”

Head of Capital Projects

North Cheshire and Mersey NHS FT

Have a project to discuss?

023 8070 1111
info@axisclc.com

Please select an enquiry type

Please enter your first name

Please enter your surname

Please enter a valid email address

Please add description of enquiry

Please agree to the terms*

Thank you! Your form has been successfully submitted. Someone will be in touch with you soon.

Error sending form.