About Us

A national leader in repairs, maintenance decarbonisation and building compliance.

Home | Case study | Amey – Weeton Barracks

Installation of External Wall Insulation

Sector

Defence

Location

North West

Service

Decarbonisation

Plus the installation of new windows and loft insulation as well as upgraded heating systems. We extended the roofs at all 36 properties to allow for extra 150 millimetres of EWI. These works form part of CLC’s 11-year contract with Amey which has recently been renewed to March 2029. This enduring relationship has seen us deliver maintenance and refurbishment works to over 12,500 married quarters including void properties for the Ministry of Defence Service Family Accommodation (SFA).

What we did

Our Energy Efficiency programme at 36 properties at Summer Grove included all associated ground / enabling works to allow for the installation of External Wall Insulation (EWI).

Specifications

  • Installation 150mm External Wall Insulation (EWI)
  • Boiler replacement
  • Electrical works
  • Replacement and repair roofs
  • Chimney demolition
  • Gable end and rafter extensions
  • Replacement of concrete cantilever canopies
  • Replacement of all doors and windows with PVCu
  • Installation of new store doors where required
  • Replace/redecorate up-and-over garage doors
  • Render garages, stores, outhouses, adjoining boundary, and dividing walls
  • Replace/refit external lighting
  • Alter fencing and gates for EWI and render installation

Project Overview

Number of weeks

49

Number of properties

36

Years of client relationship

11

+

Contract Value

£

3.9

M

This included wet weather, which was overcome by the invested in track mats. Initially the properties were all voids, but they became occupied by families during the works which altered our schedule. We worked closely with ecologists following their guidance when we discovered birds and bats in roof spaces, working around them or relocating them and acquiring the relevant licences to do so and installing bird/bat boxes on site. ‘Hedgehog Highways’ were installed into fences to ensure hedgehogs can pass freely through the gardens.

Innovations, challenges, solutions

Thanks to our strong technical capabilities and understanding of the unique needs of military housing, the duration of works was only extended by four weeks despite 12 weeks’ worth of delays.

Read the full case study

CLC has always delivered for us in terms of quality and timely delivery on the numerous streams. In addition, their customer service has always been reliable, keeping all parties informed on start dates, finish dates, progress, inductions and dealing with any issues head on, all in a nice and polite manner.

Area Billable Works Manager

Amey

Have a project to discuss?

023 8070 1111
ino@axisclcgroup.com

Please select an enquiry type

Please enter your first name

Please enter your surname

Please enter a valid email address